Project Scheduling Date Formulas

NOTE-- We retired MacNail in 2000, and replaced it with Goldenseal construction software. Goldenseal is designed for builders, remodelers and other small businesses, providing accounting, construction estimating, and project management, plus simple project scheduling. Each Goldenseal Estimate includes a simple time-line schedule, which calculates automatically from the labor hours stored in each construction Assembly.

Fixed Construction Dates-- As a Formula

If a particular schedule item cannot be started until a fixed date in the MacNail project management software:

1. Click on the item that has a fixed date.
2. Choose *Add Rows Here from the Edit menu.
3. Click in the start date cell for the new row, and type in the fixed starting date. You may want to label it as "earliest start" in column A.
4. Click in the start date cell immediately below the new row.
5. Type =MAX( . Note that the old formula in the formula bar is replaced by what you are typing.
6. Click on the start date cell in the new row that you just added. Its cell address will be added to the cell formula: which should now look something like =MAX(B34.
7. Type a comma, then click in the start date cell immediately above the new row, then type a close parenthesis. The formula bar should now read something like =MAX(B34,B33).
8. Type the Enter key, or click the mouse on the check just to the left of the formula bar.
9. The formula you just created in the MacNail construction scheduling software will now put the fixed date into the schedule, unless prior work will start even later than the fixed date.