Using MacProject Schedules |
NOTE-- We retired the MacNail construction software package in 2000, and replaced it with Goldenseal construction software. Goldenseal is a complete computer software package for builders and remodelers, providing accounting, estimating, and project scheduling features. Using Project Schedules in the MacProject Software The MacProject project management software uses boxes and lines to set up the order of work for a project. This PERT chart will show the "critical path" as a darkened or a colored line. It will help you to determine which parts of the project need the most attention-- since delays along the critical path will result in delays for the entire project. In the example above, the plumber is the on the critical path-- those lines are darkened. Other work has a certain amount of slack, which is displayed at the lower left corner of each box. For example, the electricians have about two days of slack-- they can delay a maximum of two days and not affect the project completion date. |