8" Metal Floor Truss Joist Framing

Construction ITEM DESCRIPTION

Construction estimating unit price for 8" metal floor trusses or truss joists. This style of floor framing is more likely to occur in commercial construction projects.

Unit Size

One square foot of floor framing area.

Labor Costs

We figure about 50 square feet of framing completed per hour for a skilled carpenter with an unskilled part-time helper.

Material Costs

We figure 1/2 lineal feet of truss per square foot, based on 24" joist spacing. We also include some 2x8 lumber for bracing, headers and fill-in.

Suggested Quantity

Upstairs floor area.

This unit cost includes multipliers for labor and materials, so 12" spacing will double the cost and 16" spacing will increase it by 50%. Goldenseal takes the spacing from the Structural Dimensions layout in each estimate.

Source of Construction Pricing

Turtle Creek Construction did some commercial remodeling but very little new commercial construction, so we never actually installed metal floor trusses. We use the costs for wood framing. Seems like the labor ought to be pretty close, and floor framing costs are not that big a % of overall framing costs.

Places Included

Architect Starter File, Construction Starter File, Developer Starter File, Framing Starter File.

Comments

Click here for more about Goldenseal construction estimating software.