
New & Used
Swiss Army Knives

New & Used
Leatherman Tools
Goldenseal Construction Estimating Software |
Assembly
name-- In Goldenseal Estimating Software |
add for tu-tuff vapor barr
|
Construction
Category |
SubCategory |
Concrete |
Concrete Floor Slabs |
Construction ITEM DESCRIPTION |
Concrete estimating unit cost for application
of a special purpose vapor barrier under a concrete slab, using Tu-Tuff
or similar materia
|
Unit Size |
One square foot.
|
Labor
Costs |
We figure one unskilled hour per 200
square feet of area.
|
Material
Costs |
One square foot of vapor barrier material,
with a 10% waste factor for loss and overlap.
|
Hard Construction Costs, Typical |
$.22 per square foot of vapor
barrier installed
|
Suggested
Quantity |
Slab area.
|
Source
of Construction Pricing |
Based on crew timing from one remodeling
project done by Turtle Creek Construction, using this material
(instead of our usual 6 mil or 10 mil poly sheeting).
|
Places Included |
Architect Starter File, Construction
Starter File, Developer Starter File
|
Click here for more about Goldenseal construction estimating software.
Click here for other concrete construction costs.
 |
|