Goldenseal Construction Estimating Software |
Assembly
name-- In Goldenseal Estimating Software |
add for 6 mil poly
|
Construction
Category |
SubCategory |
Concrete |
Concrete xxx |
Construction ITEM DESCRIPTION |
Concrete estimating unit cost for application
of a 6 mil polyethylene vapor barrier under a concrete slab.
|
Unit Size |
One square foot.
|
Labor
Costs |
We figure one unskilled hour per 200
square feet of area.
|
Material
Costs |
One square foot of polyethylene sheeting,
with a 10% waste factor for loss and overlap.
|
Hard Construction Costs, Typical |
$.14 per square foot of concrete
slab area
|
Suggested
Quantity |
Floor slab area.
|
Source
of Construction Pricing |
Based on crew timing on a few basement
remodeling projects done by Turtle Creek
Construction.
|
Places Included |
Architect Starter File, Construction
Starter File, Developer Starter File
|