Job Costing Report Values

Problem

report job cost by category shows actual labor under materials instead of labor.

or

Subcontractors not showing in job cost reports.

Diagnosis

They are checking values in one of the "estimated vs actual" job costing reports, and values are not right.

Solution

There is a bug in Goldenseal accounting software version 2.3 and some earlier versions. A stupid typo that puts actual labor costs into materials instead. Fixed in 2.31 and later of Goldenseal job costing software.

The subcontractor problem is in some earlier versions, fixed in 2.0 or so.