Cost Summary Switched |
Problem Cost Summary in an Estimate shows the wrong values in the equipment and material costs per unit, while using Goldenseal construction estimating software version 2.9. Diagnosis Click the Cost Summary button in a version 2.9 estimate. The cost per area for equipment and materials are switched. Solution This is a problem in 2.9 only. It's fixed in version 3.0 of Goldenseal estimating software. Users can do the following to make the switch right away:
Comments Entered 10/5/04 by Dennis Updated 11/2/2010. |