Updating Material Prices |
Material Price Updates Material prices are much more volatile than labor costs. How you handle them will depend on how much time you want to spend updating your construction estimating software cost database, and how much prices have changed. Using the Material Fudge Factor To make a quick, rough adjustment to material unit prices to handle sudden fluctuations in material prices, follow these steps:
When calculating the overall change in material prices, keep in mind that lumber makes up only 8-12% of the overall material cost of a typical stick-built construction project, and that plywood is only 2-5% of the project cost. If overall lumber prices increase by 50%, it will result in a 4 to 6% overall price increase.
|
|