Strip and Stock Topsoil Cost |
Construction ITEM DESCRIPTION Construction unit cost for stripping off the top 6" of topsoil and stocking it for later reuse. Unit Size Square foot. Labor and Equipment Costs We figure a bulldozer and operator can strip about 3,000 square feet per hour. We also include one laborer hour per 5,000 square feet. Material Costs None included. Suggested Quantity Lot area. Source of Construction Pricing Timing based on a D-9 dozer doing prep work for new pond construction. The cost may vary for different equipment sizes and soil types. Places Included Architect Starter File, Construction Starter File, Developer Starter File. Comments Click here for more about Goldenseal construction estimating software. For other sitework estimating costs, click here.
|