
New & Used
Swiss Army Knives

New & Used
Leatherman Tools
Goldenseal Construction Estimating Software |
Assembly
name-- In Goldenseal Estimating Software |
romex 6-3
|
Construction
Category |
SubCategory |
Rough Electric |
Boxes & Wiring |
Construction ITEM DESCRIPTION |
Electrical estimating unit cost for installation
of 6-3 non-metallic electrical wiring.
|
Unit Size |
One lineal foot.
|
Labor
Costs |
We figure about a skilled electrician can install
about 38 lineal feet of 6-3 heavy supply wiring per hour with a
little help from an unskilled worker.
NOTE-- This price covers 'average' conditions in new
construction or additions. Add additional labor time for snaking
wires through existing walls or for other adverse conditions.
|
Material
Costs |
One lineal foot of 6-3 romex cable plus a staple
every few feet.
|
hard
COnstruction Cost, Typical |
$0.77 per lineal foot
|
Suggested
Quantity |
No suggested quantity. Enter the length of wiring
required.
|
Source
of Construction Pricing |
Based on subcontractor crew timing from a few
electrical installations done by Turtle Creek Construction.
|
Places Included |
Architect Starter File, Construction
Starter File, Developer Starter File
|
Click here for more about Goldenseal construction estimating software.
Click here for other rough
electrical construction
costs.
 |
|