![]() |
|
||||
Estimating Cost Difference |
Problem big price difference between Hyper Estimate and MacNail construction estimating software results when importing from Hyper Estimator to MacNail Diagnosis •it will normally be 10-20% less in MacNail the first time you transfer, before
special items are added Solution If that doesn't answer the user's question, look at specific items. Is it a difference in everything? Suspect a fudge factor or locality factor. Is it in just one place-- check the specifics. Comments Entered 12/31/92 by Vinay. Updated 11/17/2010. |